Britain's LoDES Programme Closes Out: What £70 Million of Storage Demonstrators Delivered

On 17 November the Department for Energy Security and Net Zero added the last missing document to its Longer Duration Energy Storage (LoDES) Demonstration Programme page: the final report for the single project funded in Stream 1 Phase 2, Invinity Energy Systems' vanadium flow battery. The programme ran from 2021 to 2026 and made around £70 million of capital funding available across two competition streams. With all final reports now out, it is possible to compare what was promised at award with what was built.

How the programme was built

The department split the money by technology maturity. Stream 1, worth around £15 million in capital grants with matched private investment required, was for later-stage technologies at TRL 6/7 that could be demonstrated in operational environments. Stream 2, worth around £55 million through Small Business Research Initiative contracts, was for first-of-a-kind prototypes. Both streams used two phases with a down-selection between them. Lithium-ion, pumped hydro and large water tanks were excluded because they already had widely deployed commercial demonstrations in the UK.

Stream 1 Phase 1 funded 5 mobilisation projects, each with up to £1 million. B9 Energy Storage received £986,082 for a 20MW electrolyser at Ballylumford in Northern Ireland, Gravitricity £912,410.84 for a multi-weight gravity store, Subsea 7 and FLASC £471,760.00 for a hydro-pneumatic offshore store, Invinity £708,371 for a flow battery design at Bathgate and io consulting £1 million for compressed air storage in mothballed Cheshire gas cavities. No thermal storage project was funded in this stream. Only Invinity went on to Phase 2.

Stream 2 was broader. Its first phase funded 19 feasibility studies of up to £150,000 each across thermal, power-to-X and electrical storage, and 7 of those went on to Phase 2 build-and-commission contracts of up to £9.45 million. The seven awards went to Sunamp (£9,245,261), the University of Sheffield (£2,595,571), EDF R&D UK (£7,733,821), StorTera (£5,019,402), RheEnergise (£8,242,965), SynchroStor (£9,439,302) and Cheesecake Energy (£9,447,225). By our calculation those seven contracts add up to £51.72 million, the bulk of the Stream 2 envelope.

The Stream 2 technologies

The seven Stream 2 projects cover a wide range of physics. Sunamp's EXTEND project put thermal batteries and a smart heating controller into 100 homes to test how a fleet would affect one area of the network. Sheffield's ADSorB project developed modular household heat stores, with prototypes planned at the Creative Energy Homes campus at the University of Nottingham. EDF's HyDUS project adapted metal hydride storage from fusion research to hold hydrogen in bulk, with Urenco, UKAEA and the University of Bristol as partners.

On the electrical side, StorTera planned a 200kW/1.6MWh lithium sulphur single liquid flow battery at Midlothian Innovation Centre, and RheEnergise a 250kW/1MWh High-Density Hydro demonstrator. SynchroStor aimed for a grid-connected megawatt-scale pumped thermal system with 10 hours of storage. Cheesecake Energy's FlexiTanker combines thermal and compressed air storage, with pilot units planned for a Colchester microgrid alongside up to 8 MW of solar. Final reports for these projects were published in July 2026.

Invinity's flagship, as announced and as built

When the Stream 1 Phase 2 award was announced in 2023, the government described an £11 million grant for a 30 MWh vanadium flow battery of 7 MW at a key node on the National Grid. It was billed as the largest battery ever manufactured in the UK and was expected to go live in early 2025.

The final report tells a different story. A key partner withdrew in late 2024 after shifting its strategy to projects larger than 300 MWh, and Invinity could not reach binding terms with the other proposed partners. The company chose to own the project itself, with capital invested via the National Wealth Fund, and by March 2025 had approval for a revised scheme of 5.17 MW / 20.7 MWh at Uckfield in East Sussex. By our calculation the energy capacity fell by 31.0% from the original 30 MWh. The project is now named the Invinity Copwood VFB Energy Hub and sits beside 3.2 MW of separately developed solar PV.

Uckfield was chosen mainly because it already had an import/export grid connection of 5.5 MW and planning permission for a solar-plus-battery scheme. That allowed Invinity to swap lithium-ion for flow batteries through a Minor Material Amendment instead of a new application. The amendment was approved on 31 July 2025. Delays at that stage came from the council's review of flood-related drainage information, which the report says was not an objection to the technology. The drainage condition was discharged in November, before batteries arrived on site, and civil works started in October 2025.

The report puts the overall cost estimate at £20 million. As of the end of August 2025, the forward plan aimed for full system delivery by March 2026, matching the final funding milestone. Its executive summary still describes the performance and cycling data the project will produce as something that will come once Copwood is operational.

What the evidence base now contains

For policy, the programme has produced a set of engineering and delivery reports more than a set of operating data. Invinity's £11 million project had to be resized and relocated after its partner-led plan fell through, and the report's lessons are mostly about planning, grid access and land control. Invinity says it is preparing a planning readiness pack covering safety, acoustics and UK manufacturing evidence for future sites, and points to the cap and floor investment framework for longer duration storage as the next route to market.

The four-hour duration of the Copwood system places it at the short end of what the programme itself defined as longer duration storage, which the department describes as storage across days, weeks and months. The Stream 2 projects with longer durations, such as SynchroStor's 10-hour design, remain at prototype scale.