Emergency Orders as Capacity Policy: How DOE's 202(c) Docket Grew to 51 Orders in 2026

On November 13 the U.S. Department of Energy issued Order No. 202-26-51 under section 202(c) of the Federal Power Act, directing the Midcontinent Independent System Operator and Consumers Energy to keep the coal-fired J.H. Campbell plant in West Olive, Michigan available to run. The order takes effect on November 15 and lasts until February 12, 2027. It is the latest entry in a docket that the department publishes on a single page, and that page is the basis for this analysis.

Two kinds of order

Read in sequence, the 2026 entries fall into two groups. The first group consists of short orders requested by a grid operator or utility during a weather event. They typically last from one to seven days. They let the operator run specified units at maximum output regardless of air permit limits, or call on backup generators at data centres and other large customers as a last resort before an Energy Emergency Alert 3. The second group is different in kind. These orders come from the department itself, cover a named plant that its owner intended to retire, run for roughly three months and are then renewed.

The order numbers make the scale visible. The 2026 series runs from 202-26-01, issued to ERCOT on January 24, to 202-26-51 for Campbell. Fifteen of those numbers, 202-26-01 through 202-26-15, were used in the eight days from January 24 to January 31, when ERCOT, Duke Energy, ISO New England and a group of Florida utilities all applied for emergency relief within a week of each other. By our calculation that single week accounts for 29.4% of the numbered 2026 orders. Several more entries are extensions carrying an A suffix, and Puerto Rico's orders continue a separate 2025 series.

The January cluster

The January orders went to a long list of recipients. ERCOT received authority to direct backup generation at data centres and other large-load customers. Duke Energy's units in its region were allowed to run up to maximum output despite air quality limits from January 27. Florida recipients included Duke Energy Florida, the Orlando Utilities Commission, the Florida Municipal Power Agency, the city of Lakeland and Homestead Public Services, most of them for three to six days. ISO New England's order was extended on January 30 to run through February 14. All of these were requested by the entities themselves.

Summer brought a similar pattern on a smaller scale. PJM received orders in late June, mid-July, September and again from October 13 to October 16, mostly authorising it to dispatch specified units and to call on backup generation before or during an EEA 3. Southwest Power Pool and Duke Energy Carolinas received comparable short orders. On May 18, Order No. 202-26-23 authorised PJM to deploy backup generation at data centres and other major facilities. That language, used for ERCOT in January, now appears routinely in the short-duration orders.

Rolling retention orders

The second group is where the docket has its lasting effect on plant economics. Campbell has been held open by a chain of orders all year: 202-26-16 from February 17, 202-26-22 from May 19, 202-26-39 from August 17 and now 202-26-51. The department's own description notes that the plant was due to close on May 31, 2025, 15 years before the end of its scheduled design life. Each renewal tells MISO to use economic dispatch and run the plant only in the hours needed to meet the emergency, with costs kept down for consumers.

Eddystone Units 3 and 4 in Pennsylvania follow the same rhythm under PJM with Constellation Energy: Order 202-26-17 from February 24, Order 202-26-24 from May 25 and Order 202-26-40 from August 23. The current Eddystone order expires on November 20, so a further renewal would be due within days if the department keeps to its pattern. In the West, Unit 2 of the Centralia station in Washington has been covered since March, with Order 202-26-44 running from September 13 to December 11. Craig Unit 1 in Colorado appears on this year's docket from June, and Order 202-26-49 runs from September 27 to December 25.

Two Indiana plants appear on the docket from March 23. Units 17 and 18 at NIPSCO's R.M. Schahfer station and Unit 2 at CenterPoint's F.B. Culley station have each received three orders this year, the latest running from September 20 to December 18. In Florida, Unit 1 at the Orlando Utilities Commission's Stanton Energy Center has been retained under orders 202-26-26 and 202-26-42, the second expiring on November 30. Counting Campbell, the department is now holding open 7 named plants through rolling 202(c) orders, all of them fossil-fired.

Challenges on the record

The docket pages for individual orders show that the retention orders are contested. For the latest Schahfer order, the states of Minnesota, Illinois and Wisconsin and the People of the State of Michigan filed a joint motion to intervene and request for rehearing on October 16. A coalition including Sierra Club, the Citizens Action Coalition of Indiana and the Environmental Law and Policy Center filed its own request for rehearing and stay on the same date. For Craig, the State of Colorado filed a request for rehearing, motion to intervene and stay request on October 23, with several volumes of exhibits. Tri-State and Platte River Power Authority, two of the plant's own co-owners, filed a separate request for rehearing that day.

That last filing is significant because it comes from inside the ownership group. The Craig order is addressed to Tri-State, SPP and the co-owners, a group that also includes Salt River Project, PacifiCorp and Public Service Company of Colorado. Utilities being ordered to keep their own unit available are among the parties asking the department to reconsider.

Reading the pattern

Section 202(c) was written for temporary emergencies, and the short weather orders fit that description: each one follows an application, names a few days and lapses. The retention orders work differently. They are renewed on a fixed cycle, the docket records no application from the plant owner and they override retirement decisions the owners had already taken. In effect the department is using a series of three-month emergency findings to run a capacity retention programme for a small set of coal, oil and gas units.

For grid operators the practical consequence is that these units are available for dispatch at least through the winter. Campbell is covered to February 12, Craig to December 25, Centralia to December 11 and Schahfer and Culley to December 18. Whether the rehearing requests lead to court challenges will depend on how the department responds to them. The page itself was last updated on November 13, the day the Campbell order was issued.