ERCOT Sends Second-Round Batch Zero Queries to About 80% of 257 Large-Load Developers

The Electric Reliability Council of Texas has finished its first-round review of responses from 257 developers seeking to place large loads in Batch Zero, the first group of projects assessed under the eligibility criteria in Planning Guide Revision Request 145. In a filing to the Public Utility Commission of Texas on 4 November, for the Commission's 5 November open meeting, ERCOT said the first round involved approximately 5,140 questions. By our calculation that is about 20 questions per developer.

ERCOT is now issuing second-round requests for information and expects to send them to 80% of developers, or roughly 206 of the 257. The second-round requests are tailored to each developer, contain fewer questions and carry a five-business-day deadline. Transmission service providers submitted all their first-round responses on time.

The grid operator listed the problems it keeps finding: missing documentation to establish affiliate relationships, inability to show site control, failure to show that long-lead-time equipment has been ordered and will arrive before energisation, and difficulty confirming how much financial security has been posted. Finance staff, weatherisation inspectors, engineers, lawyers and internal audit are all involved in the review, with outside counsel assisting.

ERCOT must finish the review this month to file a report with the Commission on 10 December 2026. Separately, it said it will pursue good cause exceptions only for developers that needed more time to post financial security or to file a late Form W for provisional controllable load status, and it plans to seek its own exception for loads that were submitted as energised but had not energised by 10 July 2026. Those requests are expected to go to the Commission's 17 December open meeting.

Source: ERCOT letter and presentations to the PUCT, Project 59142, item 78