ERCOT Surveys 132 Utilities on Sub-75 MW Loads After Medium-Load Requests Jump

The Electric Reliability Council of Texas issued 132 requests for information on 26 October, one to each transmission and distribution service provider in its region, asking for details of every interconnection request from loads of 10 megawatts up to 75 MW received between 1 July and 31 October 2026. Responses were due at 5pm Central time on 6 November.

Loads in that range fall below the 75 MW threshold that defines a Large Load in ERCOT. ERCOT told the Public Utility Commission of Texas that its August 2026 data refresh showed a significant increase in medium loads and that utilities had informally reported a surge in requests over the summer. Its concern is that capacity taken by medium loads could be the same capacity allocated to a base load in Batch Zero, leaving little room for native load growth.

The utilities are asked to report each request's load type, megawatts, location, energisation date and ramp, whether it is behind the meter, and the developer and project names. ERCOT describes the exercise as for information purposes only and plans follow-up rounds.

ERCOT's separate data centre impact survey, presented on the same day, gives a sense of scale. Of about 177 GW of requested interconnection capacity covered by responses, large loads account for about 166 GW, leaving roughly 11 GW from medium loads. ERCOT said more than 85% of that medium-load capacity is above 50 MW. With 186 medium loads in the reviewed data set, the average works out to roughly 59 MW per facility by our calculation. Twenty of the 22 facilities reporting cryptocurrency mining as a full or partial function were medium loads.

Source: ERCOT Medium Load RFI overview, PUCT Project 59142, item 78