ISO-NE Large-Load Filing Due 16 November Would Set a 50 MW Threshold and $250/MWh Re-Dispatch Price
ISO New England and its Participating Transmission Owners Administrative Committee are preparing a Section 205 filing on large-load interconnection, due at the Federal Energy Regulatory Commission on 16 November 2026. FERC's June 18 show-cause orders gave the six RTO and ISO regions until that date, or 20 November for the Southwest Power Pool, to justify their tariffs or propose reforms. By our count, ISO-NE's deadline falls 151 days after the order.
The ISO's summary of the proposal, last updated on 9 November, defines a Large Load as a commercial or industrial customer at a single site with a gross peak demand of 50 MW or more, connecting to the transmission system at more than 60 kV. Existing loads are exempt unless their gross peak demand rises by 50 MW or more above their exempt level as of 18 June 2026.
The proposal puts large loads on notice that they must bring their own new capacity, and excludes them from the Installed Capacity Requirement. Until designated capacity resources are in commercial operation, a large load can take Interim Contract Demand Service for up to seven years. The ISO would set a Non-Firm Large Load Re-Dispatch Price of $250 per megawatt-hour; non-firm large loads bidding at or below that level are dispatched down during monthly peaks when locational prices exceed it. The netting threshold for behind-the-meter generation is set at 0 MW, which in effect bars a large load from netting its demand against on-site generation.
The ISO's application and study processes for large loads would be implemented on 1 June 2027, which by our calculation is 197 days after the filing date. Answers to the RTO filings are due 30 days after each submission, according to FERC.
Sources
- ISO New England, Large Loads Integration Proposal Information (summary, updated 9 November 2026)
- FERC, Cost transparency and customer protection initiatives in the June 2026 show cause orders for large load interconnections
- FERC, Order Instituting Proceeding Under Section 206, Docket EL26-71-000 (18 June 2026)