NEPRA Closes Saif Power Case From January 2023 Blackout After 1,376 Days

Pakistan's National Electric Power Regulatory Authority has closed enforcement proceedings against Saif Power Limited arising from the plant's restart during the national grid collapse of 23 January 2023. The order, dated 30 October 2026, accepts the company's reply to a show-cause notice and imposes no penalty.

The system collapsed at 07:34 on 23 January 2023 and was fully restored about 20 hours later. According to System Operator data cited in the order, supply at Saif Power's bus bar was restored at 22:35 that evening. The plant was instructed to synchronise its gas turbine GT-1 at 23:26 and its steam turbine at 00:50 on 24 January. It synchronised them at 01:30 and 01:08, delays of two hours and four minutes and 18 minutes respectively.

NEPRA issued an explanation notice in September 2023, rejected the company's reply in December 2024 and issued a show-cause notice the same month. Saif Power argued that its obligations to follow notices to synchronise are governed by its power purchase agreement, that the power purchaser had already penalised it, and that the delay came from automated start-up sequencing and safety requirements. A hearing was held on 8 August 2025.

The Authority concluded that the matter is substantially addressed by the contractual framework and that the record does not show circumstances warranting a penalty. It also cited the need for a consistent approach to matters arising from the same system event. By our count, the closing order came 1,376 days after the blackout and 448 days after the hearing.

Source: NEPRA order: show cause notice to Saif Power Limited (30 October 2026)