Ofgem has directed changes to the variable values in Sizewell C's Price Control Financial Model for the 2026 annual revenue setting process, in a decision dated 9 November. The values feed the calculation of the nuclear project's allowed revenue under its regulated asset base licence.

The annex spreadsheet sets the cost of debt adjustment at £255.8 million for 2025-26, £258.8 million for 2026-27 and £186.4 million for 2027-28, all in 2024/25 prices. By our calculation these total £700.9 million, and the 2027-28 figure is 28% lower than the year before. The social benefits and communications allowance rises from £3.1 million to £7.3 million and then £10.4 million, about 3.4 times the first-year value.

Ofgem also published the royalty fee RAB addition outside the corporation tax regime, £1,579.8 million in nominal terms for 2025-26, after concluding that the figure is already in the public domain. It had redacted the value in its October proposal.

The regulator received one response, from Sizewell C Ltd, which supplied updated values for five variables. Ofgem revised the cost of debt adjustment and the funded decommissioning programme allowance to reflect more timely data. It decided not to set actual supplemental revenue for 2025-26, telling the company to leave the value blank while further work is done after the revenue setting process, and trimmed forecast supplemental revenue accordingly.

Source: Ofgem: Direction to modify the Sizewell C Price Control Financial Model

Sources