Chile's 103 MW Huatacondo Solar Plant Still Offline Nearly Three Months After Cyberattack

The 103 MW Huatacondo solar plant in Chile's Tarapacá region and its 98 MW/312 MWh battery system are still cut off from the national grid almost three months after a cyberattack, according to pv magazine. The National Electric Coordinator said it triggered its disconnection protocol to protect the system after the operator alerted it, and that an investigation continues.

The coordinator's daily report for 14 November listed both the plant and the battery at 0% availability as forced disconnections, citing the same cause logged on 27 August under request SDCF 2026100475. Because the battery is still being commissioned, its outage does not count as an interruption of commercial operation. The battery's rating implies about 3.2 hours of storage at full output, by our calculation.

Broadcaster T13 dated the attack to 26 August, a day before the disconnection request.

On 11 November deputy Cristián Araya Lerdo de Tejada asked the Public Security and Energy ministries, in two formal letters, for information. He asked whether a cyber origin had been technically confirmed, which systems were affected, from SCADA to inverters and battery management, and when the plant would reconnect. As of 16 November the Chamber of Deputies had recorded no reply to either request, and no technical findings had been made public, pv magazine reported.

Source: pv magazine