Kent Expects Record Backlog After Nearly $3 Billion at End-2025 as Gulf Repairs Add Work
Kent, the Dubai-based energy engineering contractor owned by Saudi Arabia's Nesma & Partners, expects to close the year with its largest order backlog yet, according to an interview its chief executive John Gilley gave The National in Abu Dhabi. The company is on course for its revenue target of about $1.5 billion.
The backlog stood at nearly $3 billion at the end of 2025, much of it in the Gulf. The war that began in late February has disrupted shipments through the Strait of Hormuz and damaged energy plants across the region, and Kent is assessing damage for producers in Saudi Arabia, Qatar and the UAE. Rystad Energy has estimated that restoring damaged infrastructure could cost up to $58 billion, The National reported.
Work with Adnoc Gas continues, including a $1.1 billion contract to expand the Asab and Buhasa gas processing plants inside Adnoc Gas's $5 billion Rich Gas Development project. That single contract equals 22% of the programme's value by our calculation. Gilley said supply chain bottlenecks had slowed progress but that Kent still aims to finish on schedule.
He described Iraq as a very large market for the company as international oil companies expand there.
Producers are also speeding up routes that avoid Hormuz: Saudi Aramco has begun expanding its East-West pipeline to the Red Sea, and Adnoc is accelerating a new West-East pipeline to Fujairah on the Gulf of Oman, according to the report.