NYSERDA Opens Second 1 GW Bulk Storage Round After First Awards Reached 950 MW

The New York State Energy Research and Development Authority (NYSERDA) has launched the state's second Bulk Energy Storage solicitation, aiming to procure about one gigawatt of grid-scale storage, according to its announcement of 12 November. Proposers must first file a Step One eligibility application by 3:00 p.m. ET on 15 December 2026, after which eligible applicants will be invited to submit full bids.

Contracts pay through Index Storage Credits, set up in the Public Service Commission's 2024 Energy Storage Order. NYSERDA will not pay for credits until projects are permitted, installed and operating and have passed peer review and quality assurance inspection.

The round is one of at least three annual solicitations meant to secure three gigawatts of bulk storage toward the state's goal of six gigawatts of storage by 2030. The first solicitation produced eight contracted projects that will add 950 megawatts once running, which covers 31.7% of the 3,000 megawatts bulk target by our calculation.

NY Green Bank is offering financing to developers alongside the solicitation. At least 35 percent of off-site retail and bulk storage projects supported by NYSERDA are planned for downstate New York, where the authority expects them to cut peaker plant emissions.

Source: 2026 Solicitation Announced as Part of Energy Storage Roadmap | NYSERDA (nyserda.ny.gov)

Sources