PJM Files Ride-Through Rules for Data Centres After 3,900 MW Load-Transfer Event
PJM Interconnection filed proposed tariff revisions with the Federal Energy Regulatory Commission on November 16 in Docket No. ER27-522-000, setting voltage and frequency ride-through requirements for what it calls Large Computational Loads. The filing defines these as Large Loads containing 25 MW or more of computational load and responds to FERC's June 18 Show Cause Order, which preliminarily found that PJM's tariff appeared to lack operational requirements for transmission customers serving large loads.
The grid operator cites three events in which data centres switched away from the grid during voltage disturbances: about 1,500 MW on July 10, 2024, 1,800 MW on February 17, 2025 and 3,900 MW on July 22, 2026. By our calculation the latest event was 2.6 times the size of the first. PJM says such transfers can affect voltage and frequency on a scale comparable to losing several large generating units.
PJM asks for an effective date of January 16, 2027, and an order by January 15. Ramp rates, telemetry, remote disconnection and other requirements would be set out later in its Manuals.
In a second filing the same day, PJM proposed a Fast Energization process that studies new generation and large loads together, which it says would cut projected study timelines from two years to one, according to its Inside Lines announcement. That filing adds new transmission services for data centres, asks for a 60-day comment period and seeks a FERC order within 120 days.