Back to News

China

Vegetation at China's 21 GW Talatan Solar Cluster Rose 28.4% Above Pre-Build Levels

Vegetation inside the 21 GW Gonghe Talatan solar cluster in China's Qinghai province recovered within two years of construction and then exceeded earlier levels, according to a Hohai University study reported by pv magazine. The normalised difference vegetation index (NDVI) was 19.9% above pre-construction levels in the second year and averaged 28.4% higher from the second to the fifth year.

The site is high and dry: an average elevation of about 2,920 meters, 303 mm of rain a year and roughly 1,800 mm of evaporation. Nearly 88% of the rain falls between May and September, which works out to about 267 mm in those five months by our calculation.

The team combined four Beijing-3 images from May to August 2025 at 1.2-meter resolution with Landsat records from 2008 to 2025. Across 158 plant sites, NDVI inside the plants was 11.5% higher than in control strips up to 120 meters outside, and Landsat comparisons from 2024 to 2026 showed gaps of 3.5% to 10.7% in all 12 monthly checks. Plants finished between 2013 and 2018 showed gains of 14.1% to 35.9%.

The authors pointed to shade, lower evaporation and slower wind as possible causes, alongside panel-cleaning water and reseeding, but did not test these directly. They said climate variability, satellite uncertainty and the absence of field measurements limit the results, which were published in the journal Information Geography.

Source: pv magazine

Sources