India Passes 200 GW of Renewables: Halfway to 2030 in Capacity, Much Less in Delivery
India's renewable generating capacity has crossed 200 GW. A government release on 13 November 2024, drawing on Central Electricity Authority data, put renewable capacity at 203.18 GW at the end of October, up 24.2 GW or 13.5 per cent in a year from 178.98 GW. Including 8,180 MW of nuclear, non-fossil capacity reached 211.36 GW. With total installed capacity at 452.69 GW, renewables, counted to include large hydro, accounted for more than 46.3 per cent of the fleet.
The milestone invites a straightforward reading: India is on track for its target of 500 GW of non-fossil capacity by 2030. Adding 24 GW a year will not take India from roughly 211 GW to 500 GW in six years. Rajasthan leads with 29.98 GW, followed by Gujarat at 29.52 GW, Tamil Nadu at 23.70 GW and Karnataka at 22.37 GW. India's renewable tenders have been substantial, with central agencies issuing large volumes of auctions annually.
Many distribution companies are already contracted for more power than they need in some hours, especially at midday. That is the easiest number to report and the least informative about outcomes. The release cites IRENA's 2024 review estimating about 1.02 million renewable energy jobs in India in 2023, with hydropower the largest employer at around 453,000 and solar PV at about 318,600. India added 9.7 GW of solar PV in 2023 by IRENA's count, ranking fifth globally for new installations, with cumulative capacity of 72.7 GW at the end of that year on IRENA's basis.
Production-linked incentives and import duties have expanded domestic module capacity, and the approved list of models and manufacturers restricts many projects to domestic modules. India has built an industry that can deliver more than 20 GW of renewable capacity a year, and the four leading states have shown what resource-rich regions can do. Transmission must lead generation rather than follow it, especially out of Rajasthan and Gujarat.